Kharagpur Division has completed and dedicated a new 6 Mtr wide Foot Over Bridge for the rail users and passengers at Panskura station. This will ensure the smooth flow of traffic at this very busy station of the sub urban section.
On Thursday evening, the new 6 Mtr wide FOB connecting the north side circulating area to Platform no. 5&6 was opened for the public use by the railways. This will facilitate the railway users to safely and comfortably reached the platforms to catch their train and after completing their journey they can easily move out of the station towards the market through the circulating area.
The daily average footfall of passengers at the busy Panskura station is about 30,000. Students, traders, employees and passengers from various segment of the society travel daily from this important station of the suburban section. The existing Foot over Bridge was a bit narrow and often get congested during the peak office hours. This new 6 Mtr wide FOB will ease of the traffic flow even during the peak hour.
Panskura station is also being develop as an Amrit Station. It will boost of new modern and advanced facilities and amenities once the work is completed. Railways is continuously adding more facilities to provide the passengers a safe and comforting experience during their journey.
CONTINUATION OF SPECIAL TRAINS
Kolkata, 26th July, 2024
With a view to clear the extra rush of passengers, it has been decided to continue the running of Special Trains as per the given schedule:-
- 02837 Santragachi-Puri Special will continue to run till 25.10.2024
- 02838 Puri-Santragachi Special will continue to run till 26.10.2024
- 08011 Bhanjpur- Puri Special will continue to run till 31.10.2024
- 08012 Puri-Bhanjpur Special will continue to run till 01.11.2024
- 08007 Shalimar-Bhanjpur Special will continue to run till 31.10.2024
- 08008 Bhanjpur-Shalimar Special will continue to run till 02.11.2024
- 02839 Shalimar-Puri Special will continue to run till 27.10.2024
- 02840 Puri-Shalimar Special will continue to run till 28.10.2024
- 02847 Santragachi-Digha Special will continue to run till 26.10.2024
- 02848 Digha-Santragachi Special will continue to run till 26.10.2024
- 02897 Santragachi-Digha Special will continue to run till 27.10.2024
- 02898 Digha-Santragachi Special will continue to run till 27.10.2024
- 08103Tatanagar-Varanasi Special will continue to run till 29.08.2024
- 08104Varanasi –Tatanagar Special will continue to run till 30.08.2024
- 02863 Howrah-Yesvantpur Special will continue to run till 15.08.2024
- 02864 Yesvantpur-Howrah Special will continue to run till 17.08.2024
………
DUE TO DEVELOPMENTAL WORKS IN ADRA DIVISIONKolkata, 26th July, 2024In view of developmental works in Adra Division, the following trains will be regulated as under:Cancellation of Trains:
08680/08679 Adra-Midnapore-Adra MEMU Special, journey commencing on 30.07.2024, 02.08.2024 and 04.08.2024 will remain cancelled.08671/08672 Adra-Bhaga-Adra MEMU Special, journey commencing on 02.08.2024 will remain cancelled.Short Termination/Short Origination of Trains:
03594/03593 Asansol-Purulia-Asansol MEMU Special, journey commencing on 29.07.2024, 30.07.2024, 31.07.2024 03.08.2024 & 04.08.2024 will be short terminated at/short originated from Adra.
18024/18023 NSCB Gomoh-Kharagpur-NSCB Gomoh Express, journey commencing on 02.08.2024 will be short terminated at/short originated from Chandrakona Road.
08174/08652 Tatanagar-Asansol-Barabhum MEMU Special, journey commencing on 29.07.2024, 01.08.2024 & 02.08.2024 will be short terminated at/short originated from Adra.
Diversion of Train:
18601 Tatanagar-Hatia Express, journey commencing from 29.07.2024 to 04.08.2024 will run on diverted route Chandil-Gunda Bihar-Muri.*******